Work is set to begin this week on 54 miles of major roads in unincorporated Sonoma County. Improvements range from rebuilding roads to treatments that keep good roads in a good condition. This work will enhance a total of 255,515 average daily vehicle trips; however the construction will have unavoidable traffic impacts.
“The investments we make in our roads improve the daily lives of Sonoma County residents,” stated Sonoma County Board of Supervisors Chairwoman Shirlee Zane. “We will minimize traffic impacts to the greatest extent possible, while still working efficiently to protect our tax payer’s investment. We are grateful to neighbors, commuters, drivers, bicyclists and pedestrians for their patience through construction.”
Below is a summary of which roads will be under construction, and the type of work that can be expected. For details on which sections of road will be affected, traffic impacts, and weekly schedule updates visit http://sonomacounty.ca.gov/TPW/Projects/Current-Paving/.
Fog Seal
Adobe Road, East Washington Street to Frates Road
D Street, Petaluma City Limit to end of overlay
Napa Road, Eighth Street East to Hwy 12/121
Old Redwood Highway, Town of Windsor to City of Healdsburg
Porter Creek Road, NE of Porter Creek Bridge to end of overlay
Slurry Seal
Adobe Road, Corona Road to East Washington Street
Lakeville Road, Highway 37 to Old Lakeville Road 2
Mark West Springs Road, Ursuline Road to unimproved sections
Occidental Road, Highway 116 to city of Santa Rosa
Petaluma Blvd North, City Limits to Bridge
River Road (near Forestville), Rio Nido Bridge to Trenton Road
Chip Seal
Dutcher Creek Road, Dry Creek Road to Cloverdale City Limit
Geysers Road, Highway 128 to Red Winery Road
Ludwig Avenue, Llano Road to South Wright Road
Lytton Springs Road, Dry Creek Road to Healdsburg Avenue
Mill Station Road, Occidental Road to Highway 116
Watertrough Road, Bodega Highway to Pleasant Hill Road
Remove and Replace
Boyes Boulevard, Arnold Drive to Highway 12
Lovall Valley Road, Fourth Street East to Lovall Valley Road
Asphalt Overlay
Adobe Road, Frates Road to Highway 116
Brooks Avenue, Bucks Road to East Robles Road
Bucks Road, Santa Rosa Avenue to Brooks Avenue
Crocker Road, River Road to Cloverdale City Limit
River Road (near Cloverdale), Big Sulphur Creek Bridge to Geysers Road
River Road (near Cloverdale), Crocker Road to Big Sulphur Creek Bridge
El Dorado, Los Banos Drive to Riverside Drive
Healdsburg Avenue, City Limit to Alexander Valley Road
Stony Point Road, City Limit to Rainsville Road
Cold In-Place Recycling
5th Street West, Leveroni Road to City Limit
Arnold Drive, Leveroni Road to Craig Avenue (end of BWC)
Full Depth Reclamation
Cazadero Highway, Highway 166 to Austin Creek Road
Mill Station Road
Watertrough Road
Due to the unprecedented storms this winter, and the need to coordinate with projects by other Agencies, the 2017 program has been divided into phases. The 54 miles under construction this summer are part of a 97-mile program approved by the Sonoma County Board of Supervisors last year.
— County of Sonoma